Wyndham Grand Batumi Gonio. Aqua

Real estatePublished Updated 1 min read0 views
Share:Link copied
Wyndham Grand Batumi Gonio. Aqua

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
Installation of electrical system, 16th floor.

2. Facade works.
Insulation of the facade on balconies, 11, 13, 16 floors.

3. Waterproofing works, 2nd floor.
Work on the second layer of waterproofing on the balconies.

4. Works in the workshop.
Fabrication of embedded parts.

5. Arrangement of columns and partitions of reinforced concrete frame.
On 2–9, 11–20 floors.

6. Work on the floor screed.
On the 15th floor.

7. Finishing works, 3rd floor.
Laying ceramic tiles on the balconies.

8. Diamond drilling of engineering holes.
For the device of communication systems.

9. Infrastructure building.
— Reinforcement of walls.
— Installation of formwork.