Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
Installation of power supply system, 20th floor.

2. Facade works.
— Insulation of the facade, 8–14 floors.
— Plastering of the facade, 8–14 floors.

3. Finishing works, 2, 3 floors.
Laying of ceramic tiles on balconies.

4. Plasterboard frame installation works.
Installation of drywall frame rails, framing of the frame.

5. Arrangement of mocap, 3rd floor.
Finishing works, puttying of walls.

6. Work on the roof of the building.
— Welding of struts.
— Drilling of engineering holes.

7. Infrastructure building.
— Reinforcement of walls.
— Installation of formwork.