Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Installation of power supply system, 20th floor.

2. Facade works.
Plastering of the facade.

3. Gypsum plasterboard frame installation works, 20th floor.

4. Plastering works.
Plastering of balconies.

5. Finishing works, 2, 3 floor.
Laying tiles on the balconies.

6. Work on the floor screed.
On the 8th floor.

7. Mocap works, 3rd floor.
Finishing works.

8. Infrastructure building.
Reinforcement of floor slab.