Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Installation of power supply system, 9, 19, 20 floors.
— Installation of water supply system, 11th floor.

2. Facade works.
Plastering of the facade.

3. Installation of gypsum plasterboard frame.

4. Plastering works.
Plastering of balconies.

5. Finishing works, 2, 3 floor.
Laying tiles on the balconies.

6. Work on the floor screed.
On the 8th floor.

7. Mocap works, 3rd floor.
Finishing works.

8. Arrangement of curbs for stained glass windows, 20th floor.
Concreting of curbs.

9. Infrastructure building.
Reinforcement of the floor slab.