Wyndham Grand Batumi Gonio. Aqua
1. Installation of engineering systems.
Installation of power supply system, 9th, 19th floor.
2. Installation of gypsum plasterboard framework.
Installation of partitions.
3. Diamond drilling of engineering holes.
For the device of engineering systems.
4. finishing works, 2, 3 floor.
Laying tiles on the balconies.
5. Work on the device of floor screed.
On the 7th floor.
6. Plastering works.
Plastering on the balconies.
7. Mocap works, 13th floor.
Finishing works.
8. Infrastructure building.
Reinforcement of the floor slab.