fbpx

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Installation of power supply system, 9th floor.
— Installation of water supply system, 3–5 floors.
— Installation of ventilation system, 11–13 floors.

2. Facade works.
— Facade insulation, 8–14 floors.
— Plastering of the facade, 8–14 floors.

3. Floor screeding works.
On the 11th floor.

4. finishing works, 2, 3 floor.
Laying ceramic tiles on the balconies.

5. Works on installation of gypsum plasterboard frame, 12, 16 floor.

6. Arrangement of mocap, 3 floor.
Finishing works.

7. Works on the roof of the building.
— Manufacturing and installation of props.
— Drilling of engineering holes.

8. Works on the device of elevator shafts.
Plastering works.

9. Infrastructure building.
— Reinforcement of walls.
— Installation of formwork.