Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Installation of storm water drainage, 2–5 floors.
— Electrical installation, 15–17 floors.

2. Facade works.
Facade insulation, 3rd floor.

3. Plastering works, 9, 14, 17, 18 floors.
Plastering of balconies.

4. Installation of elevator shafts.
— Laying gas-block in the portals of elevator shafts, 12–14 floor.
— Installation of lighting, 16–20 floors.

5. Work on waterproofing.
— On the balconies, 20th floor.
— On the roof of the building preparatory work for the application of waterproofing.

6. Infrastructure building.
Reinforcement of walls.