Wyndham Grand Batumi Gonio. Aqua
1. Installation of engineering systems.
— Installation of storm water drainage system, 2–5 floors.
— Electrical installation works.
— Installation of ventilation system, 15–17 floors.
2. Facade works.
Facade insulation, 3rd floor.
3. Plastering works, 9, 14, 17, 18 floors.
Plastering of balconies.
4. Installation of elevator shafts.
Installation of lighting, 16–20 floors.
5. Work on the floor screed.
On the 9th floor.
6. Waterproofing works.
On the roof of the building preparatory work for the application of waterproofing.
7. Infrastructure building.
Formwork arrangement of the floor slab.