Wyndham Grand Batumi Gonio. Aqua
1. Installation of engineering systems.
— Installation of storm water drainage system, 7–9 floors.
— Installation of sewerage system, 15th floor.
2. Facade works.
Insulation of the facade, 3–6 floors.
3. Plasterboard frame installation, 2–9 floors.
Installation of partitions.
4. Plastering works, 4–9 floors.
Plastering of balconies.
5. Installation of elevator shafts.
— Installation of lighting.
— Laying of
6. Work on waterproofing.
On the roof of the building preparatory work for the application of waterproofing.
7. Infrastructure building.
Reinforcement works.