1. Installation of engineering systems.
Installation of ventilation system, 15th-20th floor.

2. Facade works.
Insulation of the facade on balconies, 4, 11, 13 floors.

3. Waterproofing works, 4–5 floors.
Work on the second layer of waterproofing on the balconies.

4. Works in the workshop.
Fabrication of embedded parts.

5. Masonry works.
Masonry block of elevator portals.

6. Plasterboard frame installation works.
Closing of the frame, 19th-20th floor.

7. Work on the floor screed.
On the 15th floor.

8. Closure of arches.
On the 20th floor.