Wyndham Grand Batumi Gonio. Aqua

Real estatePublished Updated 1 min read0 views
Share:Link copied
Wyndham Grand Batumi Gonio. Aqua

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
Installation of ventilation system, 17th-18th floor.

2. Facade works.
Insulation of facade on balconies, 4, 11, 13 floors.

3. Waterproofing works, 4–5 floors.
Work on the second layer of waterproofing on the balconies.

4. Works in the workshop.
Fabrication of embedded parts.

5. Masonry works.
Masonry block of elevator portals.

6. Plasterboard frame installation works.
Closing of the frame, 20th floor.

7. Work on the floor screed.
On the 16th floor.

8. Masonry works.
Masonry block of ventilation shafts.

9. Arrangement of mocap, 3rd floor.
Puttying of walls.

10. Infrastructure building.
Reinforcement of walls.