Wyndham Grand Batumi Gonio. Aqua

1. Installation of utilities systems.
— Wiring, the 12th — 15th floor.
— Installation of water supply system, the 11th -15th floors.
— Ventilation system installation, the 20th floor.

2. Facade works.
— The facade winterization on the balconies, the 3rd, 5th, 14th floors.

3. Installation of drywall framing.
— Installation of frame guides for drywall partitions, the11th — 12th floors.
— Sheathing of the drywall frame, the 16th — 17th floors.

4. Floor screeding.
On the balconies and in the units, the 17th floor.

5. Installation of the suspended ceilings.
On the 5th — 6th floors.

6. Waterproofing, on the 2nd- 5th floors.
On the balconies.

7. Roofing.
Installation of embedded parts and supports.

8. Diamond drilling of the engineering openings, the 2nd, 5th, 8th floors.
Marking and drilling is carried out, which is necessary for the installation of engineering systems of the future hotel.

9. Workshop.
Fabrication of the embedded parts.

10. Fabrication and installation of doors on the floors.
The 2nd — 20th floors.

11. Infrastructure building.
— Ongoing pit excavation, namely: reinforcement of the slab.