Wyndham Grand Batumi Gonio. Aqua
1. Installation of utilities systems.
— Wiring, the 13th — 15th floor.
— Ventilation system installation, the 20th floor.
2. Facade works.
— The facade winterization on the balconies, the 3rd, 5th, 20th floors.
3. Installation of drywall framing.
— Sheathing of the drywall frame, the 6th — 8th floors.
4. Floor screeding.
On the balconies and in the units, the 15th — 16th floors.
5. Installation of the suspended ceilings.
On the 5th — 6th floors.
6. Roofing.
Installation of embedded parts and supports.
7. Diamond drilling of the engineering openings, the 1st, 4th, 7th floors.
Marking and drilling is carried out, which is necessary for the installation of engineering systems of the future hotel.
8. Workshop.
Fabrication of the embedded parts.
9. Fabrication and installation of doors on the floors.
The 2nd — 20th floors.
10. Infrastructure building.
— Ongoing pit excavation, namely: reinforcement of the slab.