Wyndham Grand Batumi Gonio. Aqua

Real estatePublished Updated 1 min read0 views
Share:Link copied
Wyndham Grand Batumi Gonio. Aqua

Wyndham Grand Batumi Gonio. Aqua

1. Installation of utilities systems.
— Wiring, the 14th floor.
— Installation of water supply system, the 13th — 15th floors.

2. Facade works.
— The facade winterization on the balconies, the 3rd, 5th, 12th, 20th floors.

3. Installation of drywall framing.
— Installation of frame guides for drywall partitions, the 19th -20th floors.
— Sheathing of the drywall frame, the 11th floor.

4. Masonry works.
On the 2nd — 20th floors.

5. Floor screeding.
On the balconies and in the units, the 15th — 16th floors.

6. Fabrication and installation of the doors by floors.
On the 2nd — 20th floors.

7. Workshop.
Fabrication of the embedded parts.

8. Infrastructure building.
Reinforcement of the floor slab.