Wyndham Grand Batumi Gonio. Aqua

1. Installation of utilities systems.
— Wiring, the 15th, 19th floors.
— Installation of water supply system, the 4th, 5th, 14th, 18th floors.
— Ventilation system installation, the 11th -13th floors.

2. Facade works.
The facade winterization on the balconies, the 5th, 14th, 15th, 20th floors.

3. Installation of drywall framing, the 13th — 17th floors.
Installation of frame guides for drywall partitions.

4. Installation of the elevator shafts.
Installation of reinforced concrete beams in elevator shafts.

5. Insulation.
On the balconies, the 8th-9th, 13th, 14th floors.

6. Fabrication and installation of the steel arches.
On the 9th, 19th floor.

7. Floor screeding.
On the balconies and in the units, the 18th — 20th floors.

8. Suspended ceiling installation.
On the 5th — 6th floors.

9. Diamond drilling of the engineering openings, the 9th — 11th floors.
Marking and drilling is carried out, which is necessary for the installation of engineering systems of the future hotel.

10. Infrastructure building.
— Ongoing pit excavation.
— Formwork installation on pit walls.