Wyndham Grand Batumi Gonio. Aqua
1. Installation of utilities systems.
— Wiring, the 15th, 19th floors.
— Installation of water supply system, the 4th, 5th, 14th, 18th floors.
— Ventilation system installation, the 11th -13th floors.
2. Facade works.
The facade winterization on the balconies, the 5th, 14th, 15th, 20th floors.
3. Installation of drywall framing, the 13th — 17th floors.
Installation of frame guides for drywall partitions.
4. Installation of the elevator shafts.
Installation of reinforced concrete beams in elevator shafts.
5. Insulation.
On the balconies, the
6. Fabrication and installation of the steel arches.
On the 9th, 19th floor.
7. Floor screeding.
On the balconies and in the units, the 18th — 20th floors.
8. Suspended ceiling installation.
On the 5th — 6th floors.
9. Diamond drilling of the engineering openings, the 9th — 11th floors.
Marking and drilling is carried out, which is necessary for the installation of engineering systems of the future hotel.
10. Infrastructure building.
— Ongoing pit excavation.
— Formwork installation on pit walls.