Wyndham Grand Batumi Gonio. Aqua

1. Installation of utilities systems.
— Wiring, the 15th floor.
— Installation of water supply system, piping layout for hot and cold water supply, the 7th-9th floors.
— Ventilation system installation, the 13th — 15th floors.

2. Facade works.
The facade winterization on the balconies, the 5th, 14th, 15th, 20th floors.

3. Installation of drywall framing, the 11th — 12th floors.
Installation of frame guides for drywall partitions.

4. Floor screeding.
On the balconies and in the units, the 18th floor.

5. Installation of suspended ceilings.
On the 5th — 6th floors.

6. Diamond drilling of the engineering openings.
Marking and drilling is carried out, which is necessary for the installation of engineering systems of the future hotel.

7. Roofing.
Installation of embedded parts and supports.

8. Infrastructure building.
— Ongoing pit excavation.
— Formwork installation on pit walls.
— Concrete was delivered.