Wyndham Grand Batumi Gonio. Aqua

1. Installation of utilities systems.
— Wiring, the 15th floor.
— Installation of water supply system, piping layout for hot and cold water supply, the 7th-9th floors.
— Ventilation system installation, the 20th floor.

2. Facade works.
The facade winterization on the balconies, the 5th, 14th, 16th, 20th floors.

3. Installation of drywall framing.
— Installation of frame guides for drywall partitions, the 6th — 7th floors.
— Sheathing of the drywall frame, the 11th — 12th floors.

4. Floor screeding.
On the balconies and in the units, the 17th floor.

5. Installation of the suspended ceilings.
On the 5th — 6th floors.

6. Waterproofing, on the 2nd- 7th floors.
On the balconies.

7. Roofing.
Installation of embedded parts and suports.

8. Diamond drilling of the engineering openings, the 3rd -12th floors.
Marking and drilling is carried out, which is necessary for the installation of engineering systems of the future hotel.

9. Workshop.
Fabrication of the embedded parts.

10. Infrastructure building.
— Ongoing pit excavation, namely: reinforcement of the slab.