Wyndham Grand Batumi Gonio. Aqua
1. Installation of utilities systems.
— Wiring, the 15th floor.
— Ventilation system installation, the 20th floor.
— Installation of water supply system, the 11th — 14th, 16th — 18th floors.
2. Facade works.
— The facade winterization on the balconies, the 3rd, 5th, 20th floors.
3. Installation of drywall framing.
— Installation of frame guides for drywall partitions, the 7th — 9th, 18th floors.
— Sheathing of the drywall frame, the 6th, 8th floor.
4. Installation of the suspended ceilings.
On the 7th — 8th floors.
5. Floor screeding.
On the balconies and in the units.
6. Fabrication and installation of the doors by floors.
On the 2nd — 20th floors.
7. Workshop.
Fabrication of the embedded parts.
8. Infrastructure building.
Ongoing pit excavation.