Wyndham Grand Batumi Gonio. Aqua
1. Installation of utilities systems.
— Wiring, the 19th floor.
— Installation of water supply system, the 6th -9th, 15th floors.
— Ventilation system installation, the 9th floor.
2. Facade works.
The facade winterization on the balconies, the 3rd, 11th, 13th floors.
3. Installation of drywall framing, the 11th — 18th floors.
Installation of frame guides for drywall partitions.
4. Installation of the elevator shafts.
Installation of reinforced concrete beams in elevator shafts.
5. Insulation.
On the balconies, the
6. Fabrication and installation of the steel arches.
On the 9th, 19th floor.
7. Floor screeding.
On the balconies and in the units, the 20th floor.
8. Suspended ceiling installation.
Preparation works.
9. Diamond drilling of the engineering openings, the 9th — 11th floors.
Marking and drilling is carried out, which is necessary for the installation of engineering systems of the future hotel.
10. Infrastructure building.
Ongoing pit excavation.