Wyndham Grand Batumi Gonio. Aqua

1. Installation of utilities systems.
— Wiring, the 19th floor.
— Installation of water supply system, the 6th -9th, 15th floors.
— Installation of exhaust ventilation system risers, the 7th- 8th floors.

2. Facade works.
The facade winterization on the balconies, the 3rd, 11th, 13th floors.

3. Installation of the elevator shafts.
Installation of reinforced concrete beams in elevator shafts.

4. Diamond drilling of the engineering openings, the 9th — 11th floors.
Marking and drilling is carried out, which is necessary for the installation of engineering systems of the future hotel.

5. Insulation.
On the balconies, the 8th-9th, 13th, 15th floors.

6. Fabrication and installation of the steel arches.
On the 19th floor.

7. Infrastructure building.
Ongoing pit excavation.