Wyndham Grand Batumi Gonio. Aqua
1. Installation of utilities systems.
— Wiring, the 3rd, 16th, 19th floors.
— Installation of water supply system, the 6th -9th floors.
2. Facade works.
The facade winterization on the balconies, the 3rd, 11th, 13th floors.
3. Installation of drywall framing, the 11th — 12th floors.
Installation of frame guides for drywall partitions.
4. Installation of the elevator shafts.
Installation of reinforced concrete beams in elevator shafts.
5. Insulation.
On the balconies, the
6. Fabrication and installation of the steel arches.
On the 19th floor.
7. Floor screeding.
On the balconies and in the units, the 20th floor.