Wyndham Grand Batumi Gonio. Aqua

1. Installation of utilities systems.
— Wiring, the 3rd, 19th floors.
— Installation of water piping, the 5th, 20th floors.

2. Floor screeding.
On the balconies and in the units, the 19th floor.

3.Fabrication and installation of steel arches.
On the balconies, the 6th floor.

4. Diamond drilling of the engineering openings, the roof.
Marking and drilling is carried out, which is necessary for the installation of engineering systems of the future hotel.

5. Installation of elevator shafts.
Laying of aerated blocks in the shafts.

6. Infrastructure building.
Ongoing pit excavation.