Wyndham Grand Batumi Gonio. Aqua

1. Facade works.
— Facade winterization, the 2nd, 3rd, 6th, 7th,11th, 20th floors.
— Facade plastering, the 14th — 20th floors.

2. Installation of utilities systems.
— Wiring, the 3rd, 17th — 19th floors.
— Installation of water piping, the 20th floor.
— Connecting manifolds to water supply risers, the 3rd — 9th floors.

3. Workshop fabrication of details for installation.

4. Insulation.
Balconies, the 20th floor.

5. Mockup installation, the 13th floor.
Furniture assembly. Final works.

6. Diamond drilling of the engineering openings, the roof.
Marking and drilling is carried out, which is necessary for the installation of engineering systems of the future hotel.

7. Infrastructure building.
Ongoing pit excavation.