Wyndham Grand Batumi Gonio. Family Club.
Building A
1. Installation of
— The ledges are being reinforced on the balconies, the 3rd floor.
— The ledges are being formworked on the 3rd floor.
— The ledges are being reinforced on the balconies, the 4th floor.
2. Plastering, the 1st, 3rd, 4th floors.
Plastering of inner walls.
3. Plumbing
Installation of the drainage system.
4. Installation of drywall frames, the 2nd, 3rd floors.
Installation of guides for drywall partition frames.
5. Roofing.
— Installation of Penoplex base and mesh for screeding on the roof.
— Installation of a leveling screed on the roof.
6. Facade works.
The walls are getting ready for mineral wool installation on the balconies.
7. Installation of glazing and stained glass windows.
On the 2nd floor.
Building B.
1. Masonry works, the 4th floor and the roof.
Ceramic block installation.
2. Formwork removal from the roof access structure.