Wyndham Grand Batumi Gonio. Family Club.

Block A
1. Arrangement of metal arches on balconies.
Manufacturing and installation of metal arches on balconies.

2. Facade works.
— Facade insulation, installation of mineral wool, 5th floor.
— Facade cladding.

3. Arrangement of elevator shafts.
Concreting of lintels.

4. Plastering works.
Plastering of walls of the 2nd floor.

5. Work on the device ceilings on the balconies.

6. Screed on the balconies.

Block B
1. Arrangement of boards for installation of stained-glass structures.

2. Plastering works, 5th floor.
Plastering of the facade.