Wyndham Grand Batumi Gonio. Family Club.
Block A
1. Facade arrangement.
— Works on facade insulation and partition walls on balconies.
— Plastering of the facade.
2. Installation of monolithic belt on the roof parapet.
3. Arrangement of elevator shafts.
— Installation of reinforced concrete portals in elevator shafts.
— Plastering of elevator portals.
4. Plastering works.
Plastering of internal walls, 3, 5 floors.
5. Plasterboard frame installation works.
Arrangement of guide frames of partitions.
6. Arrangement of storm water drainage.
Installation of storm water drainage drains.
7. Welding works.
Fabrication of metal arches.
Block B
1. Plastering works.
Plastering of internal walls, 2nd floor.
2. Masonry works, 5th floor.
Block masonry in ventilation shafts.