Wyndham Grand Batumi Gonio. Family Club.
Block A
1. Facade arrangement.
— Works on facade insulation and partition walls on balconies.
— Plastering of the facade.
2. Installation of monolithic belt on the roof parapet.
3. Floor screed works.
Preparatory works on balconies.
4. Arrangement of the ceiling framework on the balconies.
5. Arrangement of storm water drainage.
Installation of storm water drainage drains.
Block B
1. Plastering works.
Plastering of internal walls, 3rd floor.
2. Masonry works.
Ceramoblock masonry, 5th floor.