Wyndham Grand Batumi Gonio. Family Club.

Block A
1. Facade arrangement.
— Works on facade insulation and partition walls on balconies.
— Plastering of the facade.

2. Installation of monolithic belt on the roof parapet.

3. Arrangement of elevator shafts, 4th floor.
Installation of reinforced concrete portals in the elevator shafts.

4. Plastering works.
Plastering of internal walls, 3, 5 floors.

Block B
1. diamond drilling of engineering holes.
For the device of storm water drainage.

2. Plastering works.
Plastering of internal walls, 2 floor.

3. Masonry works, roofing.
Block masonry in ventilation shafts.