Wyndham Grand Batumi Gonio. Family Club.
Block A
1. Facade works.
Cladding of the facade with clinker tiles.
2. Plastering works.
Plastering of the walls of the 2nd floor.
3. Ceiling works on the balconies.
4. Arrangement of elevator shafts.
Concreting lintels of elevator shafts.
5. Arrangement of screed on the balconies.
Block B
1. Arrangement of boards for installation of stained glass structures.
2. Plastering works, 5th floor.
Plastering of the facade.