Wyndham Grand Batumi Gonio. Family Club.

Block A
1. Installation of engineering systems, 2–3 floor.
Arrangement of storm water drainage box frame.

2. Installation of stained glass structures.
Installation of stained glass windows and glass.

3. Facade works.
Insulation of the facade.

4. Plastering works, 2nd floor.
Plastering of internal walls.

5. Manufacturing of metal arches on balconies.

Block B
1. Plastering works.
Plastering of walls on balconies, 5th floor.