Wyndham Grand Batumi Gonio. Family Club.

Block A
1. Installation of stained glass windows, 3rd, 5th floor.
Installation of stained glass structures and glass.

2. Installation of suspended ceilings, 1 floor.
Arrangement of ceiling framework on balconies.

3. Fabrication of metal arches for installation on balconies.

Block B
1. Plastering works.
— Plastering of walls on balconies, 4th floor.
— Plastering of the roof parapet.

2. drilling of engineering holes in the elevator shafts.