Wyndham Grand Batumi Gonio. Family Club.

Block A

1. Plastering work.

Plastering of slopes, 1st and 2nd floors.

2. Waterproofing work.

Preparation of terraces for waterproofing.

3. Material acceptance.

Delivery of materials for work on the building roof.

Block B

1. Installation of monolithic sidewalls.

For subsequent installation of stained glass structures.

2. Roof work.

Installation of reinforced roof parapet and ventilation shaft.