Wyndham Grand Batumi Gonio. Family Club.

Building A
1. Facade works.
Plastering of facade walls, the 4th floor.

2. Installation of cast-in ledges on the balconies.
The ledges are being formworked and reinforced for stained glass windows to be installed.

3. Stormwater drainage system installation.
On the balconies

4. Stormwater drainage system installation.
Stormwater drainage risers are being installed on the balconies.

Building B
1. Masonry works
Ceramic block installation on the balconies of the 4th floor.