fbpx

Wyndham Grand Batumi Gonio. Family Club.

Building A
1. Installation of cast-in ledges on the balconies, the 3rd- 4th floors.
The ledges are being formworked and reinforced for stained glass windows to be installed.

2. Plastering, the 1st, 3rd, 4th floors.
Plastering of inner walls

3. Installation of stormwater drainage system on the balconies.

4. Installation of drywall frames, the 1st, 2nd floors.
Installation of guides for drywall partition frames.

Building B.
1. Masonry works, the 4th floor.
Ceramic block installation.