Wyndham Grand Batumi Gonio. Family Club.

Building A
1. Installation of cast-in ledges on the balconies.
— The ledges are being reinforced on the balconies, the 4th floor.
— Concreting the ledges on the balconies, the 4th floor.

2. Plastering, the 1st, 3rd, 4th floors.
Plastering of inner walls.

3. Installation of drywall frames, the 2nd, 3rd floors.
Installation of guides for drywall partition frames.

4. Roofing.
Installation of leveling screed on the roof.

5. Plumbing.
Installation of stormwater drainage.

Building B.
1. Masonry works, the 4th floor and roofing.
Ceramic block installation.