Wyndham Grand Batumi Gonio. Family Club.
Building A
1. Plastering, the 2nd, 3rd floors.
Priming of internal walls for plastering.
2. Cast-in belt pouring for roof parapet.
Building B.
1. Installation of ledges for the stained glass windows.
— Preparing reinforcement cage components for cast-in ledges under stained glass windows, 3rd floor.
— Installing reinforcement cages for cast-in ledges under stained glass windows, 2nd floor.
— Installing formwork for cast-in ledges under stained glass windows.
— Casting concrete for ledges under stained glass windows, 3rd floor.