Wyndham Grand Batumi Gonio. Riviera.
1. Block B. Plastering works.
Plastering of internal walls.
2. Block A. Installation of formwork and reinforcement frames for contour walls, technical floor.
3. Block A. Plasterboard frame installation works.
Arrangement of guide frames for GKL partitions.
4. Block A. Mocap works.
Installation of electrics.
5. Block A. Installation of engineering systems.
Completion of works on installation of sewerage and ventilation system.
6. Block A. Installation of monolithic belts for partitions on terraces, 3rd floor.
7. Block A. Masonry works.
Ceramoblock masonry, technical floor.
8. Block A, E. Installation of
— Installation of slopes.
— Installation of
9. Block B. Installation of waterproofing.
10. Block B, C. Installation of fireplaces.
Installation of chimneys
11. Block C. Drilling of engineering holes.
For the device of communications.
12. Infrastructure building.
Installation of stairwell slab formwork.