Wyndham Grand Batumi Gonio. Riviera.

1. Plastering.
— Plastering of inner walls in Block B.

2. Block B. Staircases installation.
— Formwork installation for the staircases.
— Concrete pouring for the staircases.

3. Block C. Installation of drywall frames.
Installation of guides for drywall partition frames.

4. Block E. Facade works.
Facade winterization.

5. Block A. Installation of utilities systems.
Installation of engineering openings for gas pipelines, installation of sleeves.

6. Block A. Waterproofing.
On the 3rd floor.

7. Infrastructure building.
— Column reinforcement.
— Formwork installation for the cast-in belt on the roof.