Wyndham Grand Batumi Gonio. Riviera.
1. Plastering.
— Plastering of inner walls in Blocks E, B the 1st- 3rd floors.
2. Block E. Facade works.
— Facade plastering.
3. Block B. Installation of staircases.
Formwork installation for the staircases.
4. Masonry works.
Ceramic block installation, in the basement.
No other construction work is underway due to weather conditions.