Wyndham Grand Batumi Gonio. Riviera.
1. Plastering.
Plastering of the walls inside the buildings A.
2. Block E. Installation of the utilities.
Plumbing — installation of sewage and air conditioning systems.
3. Block E. Facade works.
— Facade plastering.
— Facade winterization.
4. Block D. Pouring the ledges on the lents.