Wyndham Grand Batumi Gonio. Riviera.
1. Plastering.
Plastering of the walls inside the buildings A.
2. Block E. Installation of the utilities.
Plumbing — installation of sewage and air conditioning systems.
3. Block E. Facade works.
— Facade plastering.
— Facade winterization.
4. Block D. Pouring the ledges on the lents.
5. Block E. Installation of the utilities.
Plumbing — installation of sewage and air conditioning systems.
6. Installation of drywall framing.
— Installation of frame guides for drywall partitions.
7. Mockup installation in Block A, the 3rd floor.
Wiring.
8. Block A. Insulation, the 1st floor.
Installation of the insulation on the terraces.