Wyndham Grand Batumi Gonio. Villas.

Real estatePublished Updated 1 min read0 views
Share:Link copied
Wyndham Grand Batumi Gonio. Villas.

Wyndham Grand Batumi Gonio. Villas. — 1. Continuation of column reinforcement at Villa 8 and commencement of column reinforcement at Villa 9. It ensures the strength and stability of columns, preventing deformation and enhancing the building's durability. 2. Removal of formwork from the walls at Villa 16. It is required to remove temporary structures used to shape concrete walls, enabling the completion of the construction phase and preparing the walls for further finishing. 3. Installation of sewer outlets at Villas 14 and 15. 4. Backfilling of foundation walls at Villas 14 and 15.