Wyndham Grand Batumi Gonio. Villas — 1. Continuation of slab formwork installation, Villas 2 and 6 This step creates the necessary form and support for concrete pouring, ensuring the precise dimensions and durability of the slab. 2. Ongoing reinforcement of columns, Villas 10 and 11 This process strengthens and stabilizes the columns, preventing deformation and enhancing the building’s durability. 3. Removal of floor slab formwork, Villas 10 and 11 This allows for the completion of floor formation and prepares the surface for final finishing. 4. Removal of ceiling slab formwork, Villas 1 and 4 This means clearing formwork structures for further work, providing access to the slabs for finishing and installation of utilities. 5. Ongoing waterproofing of foundation interior walls, Villas 14 and 15