fbpx

Wyndham Grand Batumi Gonio. Villas.

1. Formwork installation for columns of the II floor, Villa 8.
Installation of formwork to shape the columns, essential for concrete pouring and structural formation.

2. Reinforcement:
— Columns of the II floor, Villa 9.
— Cast-in floor slabs of the II floor, Villas 2, 5.
— Reinforcement of the staircases from the 1st to 2nd floor, Villa 4

It ensures the strength and stability of the structure, preventing deformation and enhancing the building’s durability.

3. Formwork installation for the staircases from the 1st to 2nd floor, Villas 7, 6.

4. Fence installation.
— Masonry works.
— Removal of formwork from the posts and cast-in fence lintel.