Wyndham Grand Batumi Gonio. Villas

1. Formwork Installation for Stairs from 1st to 2nd Floor, Villa 10.
Installation of formwork to create the shape required for concrete pouring and structure formation.

2. Concrete Pouring of 2nd Floor Columns, Villas 10, 11.
Ensuring the strength and stability of vertical structures, forming a reliable foundation for the entire building structure.

3. Concrete Pouring of 2nd Floor Monolithic Slab, Villas 1, 7, 8, 9.
Creating a strong and even base for future floors, ensuring the required rigidity and resistance to loads.

4. Concrete Pouring of Monolithic Stairs from 1st to 2nd Floor, Villas 8, 9.
Ensuring strength and stability of structures, forming a reliable foundation for the entire building structure.

5. Masonry Works, Villa 4
Masonry of ceramic block external walls, 1st floor.