Wyndham Grand Batumi Gonio. Villas

Real estatePublished Updated 1 min read0 views
Share:Link copied
Wyndham Grand Batumi Gonio. Villas

Wyndham Grand Batumi Gonio. Villas

1. Formwork Installation for the Monolithic Slab of the 2nd Floor, Villas 7, 8, 9.
Installation of formwork to create the shape required for concrete pouring and structure formation.

2. Formwork Installation for the Monolithic Staircase
From 2nd to 3rd floor, Villa 3.
From 1st to 2nd floor, Villa 11.

Installation of formwork to create the shape required for concrete pouring and structure formation.

3. Formwork Installation for the Columns of the 2nd Floor, Villas 10, 11.
Installation of formwork to create the shape of columns required for concrete pouring and structure formation.

4. Reinforcement of the Monolithic Slab of the 2nd Floor, Villas 7, 8.
Ensures structural strength and stability, preventing deformation and increasing the durability of the building.

5. Masonry Works, Villas 2, 4
Masonry of ceramic block external walls, 1st floor.

6. Manufacturing of Reinforcement Frames for Columns of the 2nd Floor, Villa 12.