1. Formwork removal from the I floor columns, Villa 15.
Removal of formwork after concrete has hardened to complete the structure and prepare for the next stage of construction.

2. Reinforcement:
— Staircases from the 1st to the 2nd floor, Villas 5, 6.

It ensures the strength and stability of the structure, preventing deformation and enhancing the building’s durability.

3. Formwork installation for the staircases from the 1st to 2nd floors, Villas 9, 10.

4. Formwork installation for II floor slab, Villas 6, 7
Installation of formwork to create the necessary shape for concrete pouring and structural formation.

5. Cutting of reinforcement bars and fabrication of column structures for the II floor columns, Villas 12, 13.