Wyndham Grand Batumi Gonio. Aqua

Real estatePublished Updated 1 min read0 views
Share:Link copied
Wyndham Grand Batumi Gonio. Aqua

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
Installation of power supply system, 9th, 20th floor.

2. Facade works.
— Insulation of the facade, 8–14 floors.
— Plastering of the facade, 8–14 floors.

3. Floor screeding works.
On the 11th floor.

4. finishing works, 2, 3 floor.
Laying ceramic tiles on the balconies.

5. Works on installation of gypsum plasterboard frame.
Installation of drywall frame rails, framing of the frame.

6. Arrangement of mocap, 3rd floor.
Finishing works.

7. Work on the roof of the building.
— Welding of columns.
— Drilling of engineering holes.

8. Arrangement of ventilation shafts.
Plastering works.

9. Infrastructure building.
— Reinforcement of walls.
— Installation of formwork.