Wyndham Grand Batumi Gonio. Villas.
1. Masonry works.
— Ceramoblock masonry external walls of the 1st floor, villa 7, 10.
— Ceramoblock masonry exterior walls of the 2nd floor, villa 6.
2. Dismantling of the formwork of columns II floor, villa 13.
Removal of formwork after concrete curing to complete the structure and prepare for the next stage of construction.
3. Installation of temporary fencing on floor slabs, villa 5, 10, 11, 12, 14.