1. Removal of slab formwork, Villa 11.
Removal of the formwork after the concrete has cured to complete the structure and prepare for the next construction phase.

2. Column reinforcement work, Villas 14, 16.
It ensures the strength and stability of the columns, preventing deformation and enhancing the durability of the structure.

3. Installation of floor slab formwork, Villa 13.
Formwork installation to create the necessary shape for concrete pouring and structural formation.

4. Fencing
— Formwork removal from the fence poles.
— Installation of ceramic blocks.